Steam Electrolyser manufacturing almost completed

24.05.2020 | GrInHy2.0


Sunfire is manufacturing Sunfire-HyLink modules (steam electrolysis modules) and the container system (the electrolysis system) for the GrInHy2.0 project since January. In parallel the operation regime has been developed and the control software was implemented.

The Sunfire-HyLink HL200 is now almost completed and will enter the testing phase soon. Testing starts with electrical checks and safety checks and will be continued with the process commissioning. Therefore, we are now at the beginning of a very intense and exciting project stage, that will give an important outlook on the onsite operation in Salzgitter.